How Zolemba migrated from Spryker to Sylius in 6 months – with zero disruption for 90,000 customers
Zolemba is a Dutch eCommerce company with more than 15 years of experience in the European printed labels market. It serves around 90,000 customers across Europe and beyond, with eCommerce at the core of its business. In 2025, Zolemba worked with our Professional Soltuion Partner - AXON21 to replace its existing Spryker platform with Sylius. The migration was completed in six months, on time and on budget, while keeping the service running for customers throughout the transition.
How Zolemba migrated from Spryker to Sylius in 6 months – with zero disruption for 90,000 customers

6 months

from kickoff to production

95%

of custom code preserved

90,000

customers, zero disruption

The Challenge

Zolemba had reached a point where its existing commerce platform no longer matched the way the business wanted to develop.

Platform costs were increasing, feature delivery was becoming slower, and the existing architecture made further customization more difficult. At the same time, Zolemba had a large amount of custom business logic, integrations, and B2B workflows built into the platform.

The biggest constraint was time. The migration had to be completed before the next platform license renewal, leaving the team around six months to move a live enterprise eCommerce environment to a new stack.

A traditional rebuild would have meant rewriting years of custom development. Instead, the project focused on preserving as much of Zolemba’s existing business logic as possible while moving it to a more flexible foundation.

Preserving the existing business logic

One of the most important parts of the project was separating Zolemba’s custom business logic from the platform it had been built into.

Using AI-assisted code extraction through the AXON21 AI Delivery Platform, the team was able to migrate 95% of the custom code to the new stack instead of rebuilding it from scratch.

This significantly reduced the scope of the replatforming and made the six-month delivery timeline possible.

Six months from kickoff to production

The project ran from May to October 2025 and covered the full migration process:


AXON21 managed the commerce stack across application, infrastructure, architecture, and delivery, which helped keep decisions and implementation within one team throughout the project.

Results

The migration gave Zolemba a more flexible commerce foundation while preserving most of the custom development built over previous years.

Key results include:

  • 6 months from kickoff to production
  • 95% of custom code preserved
  • 90,000 customers migrated without disruption
  • zero downtime during cutover
  • migration completed on time and on budget
  • recurring platform license costs removed
  • faster workflows reported by internal teams after launch

The new Sylius-based setup gives Zolemba more control over its commerce stack and a stronger foundation for further B2B development.